Ok. Got itIndependent political analyst, JP Landman, looks at the two things at Eskom that concern South Africans most – at a mountain of debt and load-shedding.
This Political Research Note was prepared by JP Landman in his personal capacity. JP is an independent political and economic analyst and the opinions expressed in this article are his own and do not reflect the views of the Nedbank Group.
May we have your feedback? As a reader of this research note, we are interested in what you think the four or five things are that South Africa needs to get right in the next five years. Your answers will enable us to do some longitudinal research. Please give it some thought and drop us a line at replies@nedbankprivatewealth.co.za. |
A mountain of debt and load-shedding. These are the two things at Eskom that concern South Africans most. In March, we wrote about energy and Eskom in great detail, so what has changed since then?
Eskom’s debt has grown to R488 billion. The company cannot repay that from operations. However, in various public statements CEO André de Ruyter has revealed his plans on how to deal with the debt.
Several governments, international development institutions and banks are willing to replace current Eskom debt with cheaper ‘green money’, on condition that Eskom transitions from coal-fired power to cleaner energy. Governments and development institutions want to see a reduction in global emissions. Banks want to ensure that their current loans to Eskom will be repaid, so refinancing at lower rates suits them. Dealing with debt and transitioning to green energy have become two sides of the same coin.
The transition to cleaner energy is already part of South Africa’s Integrated Resource Plan (IRP), approved in 2019. It envisages the decommissioning of some 11 000 MW of coal-fired power capacity by 2030 and some 24 000 MW more after 2030. Coal will be with us for a long time, but its role will be declining.
Part of De Ruyter’s vision is that existing Eskom power plants can be refurbished as gas-fired stations, and land adjacent to power stations used for solar energy. He observes that, although the Northern Cape is ideal for solar energy, Mpumalanga has more sunshine than Germany, where solar power forms a large part of power generation. Eskom itself may form joint ventures with private companies by putting the power stations and adjacent land into joint ventures as a capital contribution, with private sector partners providing the cash to refit stations for gas or build renewable plants.
The way out of debt and to a stronger balance sheet is greener power. A target date that suggests itself for debt restructuring is the next global climate change conference in Glasgow in November 2021.
Load-shedding is determined by three things: maintenance, Medupi and Kusile coming online, and new generating capacity.
In a presentation to parliament in September, Eskom stated that ‘deep maintenance’ will be completed by March 2022. Until then, plants will be taken out of commission for proper maintenance, which can lead to load-shedding.
As we wrote in March, the cooling towers at Medupi and Kusile are 12 metres too short and must be lengthened to enable full capacity. This takes 75 days per tower. The current completion dates are 2021 for Medupi and 2023 for Kusile.
The most dramatic change since March concerns new capacity. The green light has been given for nearly 14 000 MW of new capacity to be installed by 2024. This is significant, considering that Eskom can produce a little over 30 000 MW on a good day. The 14 000 MW is part of 30 000 MW to be procured by 2030. All of it will be procured from independent producers – a big boost for investment and private sector involvement in power generation.
The 14 000 MW consists of two rounds. The first is 2 000 MW of ‘emergency power’. Following the shock of stage 6 load-shedding in December 2019, Minister of Energy Gwede Mantashe referred it to the National Energy Regulator of South Africa (Nersa) in February 2020. The regulator gave concurrence at the end of May, the procurement was gazetted in July, and the tender documents went out at the end of August. Bids will close in November and preferred bidders will be announced by 15 December, one year after the shock load-shedding. (The slow pace is exasperating for a country in load-shedding.) The power must be available by no later than June 2022.
The bid documents require that the energy must be ‘dispatchable’, meaning it can be switched on and off as power is required. Neither coal nor nuclear power plants can do that. Switching solar and wind power on and off is not really in human hands. The implication is that the 2 000 MW will be gas. Gas is 50% cleaner than coal. It fits with the vision of green power and refurbishing some Eskom power stations for gas. Existing diesel plants can also be converted to gas, making them cheaper to run.
The real boost to capacity comes from the second round: The 11 813 MW for which Nersa gave concurrence in July, which was gazetted on Friday 25 September. The bid documents will be out by end December. Realistically, 2021 will be used for the auctions and selecting the bidders, finalising contracts, and putting finance in place. Construction will probably start in 2022. Energy can flow by mid-2023.
(Again, the delays in approval are exasperating. The IRP was published in October 2019, the 11 813 MW referred to Nersa in February 2020, concurred to by Nersa in July, and gazetted only end September …)
The 2 000 MW emergency power is expected to generate investment of R80 billion by June 2022.
The investment impact of the 11 831 MW will become clear only as the auctions proceed, but it is useful to remember that 6 000 MW in renewables since 2011 has generated more than R200 billion in investment.
The IRP envisages that after 2030, more coal-fired capacity will be closed and more new capacity will be built. Apart from greener power, these plans support industrialisation and will dramatically expand the gas industry. Energy is indeed the new investment frontier in South Africa.
In 2019 President Cyril Ramaphosa announced the break-up of Eskom. Eskom met the March 2020 target date for functionally separating into three units: generation, transmission and distribution. Accounting, information technology, human resources and administrative systems are now being disentangled and reconfigured. The next big step is the legislative change to separate the three companies, probably in 2021. Connect the dots and it is clear that Eskom is under severe pressure from cabinet to make this happen as soon as possible.
The most important element of a legislative split is an independent transmission company. That will open the door to competition in generation and distribution, drive transparency in prices, squeeze inefficiencies out of the system, and pave the way for private investment in both generation and distribution. Transmission will remain state-owned and controlled.
Over the past two-and-a-half years, the Ramaphosa government took several decisions on Eskom and electricity. We summarised them in March. Since then we have seen consistent, if slow, implementation. It includes the resumption of signing independent power producer (IPP) contracts in 2018 (two months after Ramaphosa took power), the decision in 2019 to break up Eskom, substantially overcoming the resistance to such a break-up (no small political feat), the launch of the IRP with 30 000 MW of new capacity (70% of which is renewable), and the green light that has now been given for 14 000 MW to be procured. Because these decisions were spread out over two and a half years, the impact on the public mind is diffuse, but that does not make it less real.
The much talked about Treasury paper lists 10 ‘to do’ actions in respect of electricity and Eskom. Eight of them have been done or are being implemented; two are still outstanding.
If one is looking for strong political will and decisions on the economy, the energy decisions are it.
The timelines summarised above clearly illustrate that the current system is too time-consuming. In fact, one of the two outstanding items on the Treasury’s ‘to do’ list, is to ‘shorten the Nersa turnaround times’. (The other is that municipalities should be made less dependent on electricity income.)
Not mentioned in the Treasury paper, but certainly very real, is the requirement for section 34 ministerial determinations before capacity can be
installed. It makes the system very rigid. Within appropriate guidelines, producers who want to risk their capital and generate power should be allowed to do so, selling to any willing buyer. The door has been opened for municipalities to buy power from providers other than Eskom. It needs to open wider. More competition will serve everybody better.
Own generation must also be made easier and the resale of such power to other parties permitted. Currently, generation above 1 MW requires a cumbersome licensing process, restraining South Africa from using own-generation opportunities to the fullest. The Council for Scientific and Industrial Research estimates that between 2 000 MW and 5 000 MW can be installed in this way. If they are halfway correct, load-shedding can be resolved much more quickly.
This note focuses on generation only, but distribution is a big outstanding issue. Municipalities largely neglect the distribution networks, increasing breakdown risks. Distribution technology is also changing fast, offering many new possibilities. After generation, it is the next big thing to tackle.
This communication is issued by Nedgroup Private Wealth (Pty) Limited and its subsidiaries (‘Nedbank Private Wealth’) for information purposes only, and recipients should not rely on such information as advice without obtaining financial, tax or other professional advice. The information referred herein has been obtained from various sources and may include facts and events or prevailing market conditions as at the time or date of the information going to print. Nedbank Private Wealth does not warrant the completeness or accuracy of any information contained herein, nor does it not make any representation that the information provided is appropriate for use by all investors in all jurisdictions. All opinions expressed and recommendations made are subject to change without notice. Nedbank Private Wealth and its employees may hold securities or financial instruments mentioned herein. The information contained in this document does not constitute an offer or solicitation of financial services or products and Nedbank Private Wealth accepts no liability for any loss or damage of whatsoever nature including, but not limited to, loss of profits or any type of financial or other pecuniary or direct or special indirect or consequential loss howsoever arising whether in negligence or for breach of contract or other duty as a result of use or reliance on the information contained in this communication.
|